TIP Projects

TIP Project Status Report August 2018
  • U-3330 Widen Wesleyan Boulevard

    The project to add one northbound travel lane and one southbound travel lane to Wesleyan Boulevard from Benvenue Road to May Drive is approximately 30% complete. Contractors are working to have the new Sunset Avenue bridge in service in December 2018. Completion of the project is anticipated in May 2020.

  • U-3621A Widen Hunter Hill Road

    The four-lane divided highway from North Winstead Avenue to Country Club Road will be completed in July 2019. THe project is now about 60% complete.

  • U-4762 Springfield Road

    The widening of Springfield Road from US 64 Business to Leggett Road is scheduled to begin in August 2018. Springfield Road will be a three-lane road with a center lane for left turns. Curb and gutter will be added, and a sidewalk installed on the west side.